In August, CSG Justice Center staff, along with expert consultant, continued to work on the draft of the Risk Assessment Guidelines document, which included multiple project team meetings and various iterations of the draft of the guidelines document.
Previously, the project team and consultant had developed the first draft of the guidelines and shared it with the advisory group to request feedback. During the first half of August, the project team and consultant reviewed incoming feedback from the advisory group members and incorporated it into the draft document.
During the second half of August, CSG Justice Center staff held various calls with a working group participant and other connections to discuss the Risk Assessment Guidelines Project and strategies for moving the conversation forward. Additionally, the project team and consultant continued to draft and edit iterations of the Risk Assessment Guidelines document.
Please check the box next to the following questions if the answer is 'yes'.
Please enter the applicable Event Date if there is an Event associated with this TTA.
When entering an Event Date, the Time is also required.
If the TTA is targeted to a particular audience or location, please complete the questions below.
Milestones are an element, activity, work product, or key task associated with completing the TTA (e.g. kick-off meeting, collect data from stake holders, deliver initial data analysis).
Please complete the fields below, if applicable, to create a milestone for this TTA.
• 8/03 – Call with project team and consultant to discuss the first draft of the guidelines document and thoughts from the team, as well as next steps regarding the working group and project team action steps.
• 8/10 – Call with project team and consultant to discuss feedback from working group members on the first draft of the guidelines document, how this feedback should be incorporated, and any project team action steps.
• 8/17 – Call with project team and consultant to discuss the updated draft of the guidelines document and possible next steps for this deliverable. Project team action items included an additional round of redrafting from consultant which would be followed by editing from the CSG Justice Center staff.
• 8/19 – Call with working group participant and other connections to discuss the Risk Assessment Guidelines Project and strategies for moving the conversation forward.
• 8/20 – Call with working group participant and other connections to discuss the Risk Assessment Guidelines Project and strategies for moving the conversation forward.
• 8/25 – Call with working group participant and other connections to discuss the Risk Assessment Guidelines Project and strategies for moving the conversation forward.
Please respond to the Performance Metrics below. The Performance Metrics questions are based on the TTA Type indicated in the General Information section of the TTA.
Please submit a signed letter of support from your agency’s executive or other senior staff member. The letter can be emailed to or uploaded with this request. The letter should be submitted on official letterhead and include the following information:
- General information regarding the request for TTA services, i.e., the who, what, where, when, and why.
- The organizational and/or community needs specific to the request for TTA services.
- The benefits or anticipated outcomes from the receipt of TTA services.
By submitting this application to BJA NTTAC, I understand that upon approval of this application for TTA, the requestor agrees to keep BJA NTTAC informed of any circumstances that may impact the delivery of the TTA, including changes in the date of the event, event cancellation, or difficulties communicating with the assigned TTA provider.