The NCJA project team reviewed the 2018 Strategic Plan submitted by the Hawaii SAA. This plan was submitted in the year prior to the new strategic planning requirement mandated by the Justice for All Reauthorization Act for 2019 applications.
Plan Strengths:
Hawaii has a very strong plan with a tremendous amount of information and supporting data. The correct stakeholders were clearly engaged. Priorities were set using best practices and are supported by stakeholder information. There is a large amount of supporting baseline data. There is a clear path for sub-grantees to receive funds. Objectives include ongoing feedback loop with community and stakeholders and ongoing re-assessment of needs.
Plan Opportunities:
1) Although there is great supporting data it would be beneficial if there was so more up to date data to go beyond 2015.
2) There is a lot of information on how past funds were spent and a great section on resource needs for the future, however there did not seem to be specifics on what exactly the resource needs will be moving forward in dollar amounts or percentages.
3) I did not see much mention of barriers.
state administering agencies
Please check the box next to the following questions if the answer is 'yes'.
Please enter the applicable Event Date if there is an Event associated with this TTA.
When entering an Event Date, the Time is also required.
If the TTA is targeted to a particular audience or location, please complete the questions below.
Milestones are an element, activity, work product, or key task associated with completing the TTA (e.g. kick-off meeting, collect data from stake holders, deliver initial data analysis).
Please complete the fields below, if applicable, to create a milestone for this TTA.
Using a standardized scoring rubric reviewed by BJA, the NCJA team reviewed the plan submitted by the SAA for their 2018 Byrne JAG grant application. This review serves as a baseline prior to new reporting requirements implemented with the 2019 Byrne JAG applications. Review of the plan and notes related to strengths, weaknesses and opportunities.
Please respond to the Performance Metrics below. The Performance Metrics questions are based on the TTA Type indicated in the General Information section of the TTA.
Please submit a signed letter of support from your agency’s executive or other senior staff member. The letter can be emailed to or uploaded with this request. The letter should be submitted on official letterhead and include the following information:
- General information regarding the request for TTA services, i.e., the who, what, where, when, and why.
- The organizational and/or community needs specific to the request for TTA services.
- The benefits or anticipated outcomes from the receipt of TTA services.
By submitting this application to BJA NTTAC, I understand that upon approval of this application for TTA, the requestor agrees to keep BJA NTTAC informed of any circumstances that may impact the delivery of the TTA, including changes in the date of the event, event cancellation, or difficulties communicating with the assigned TTA provider.
Please call [site:phone] if you need further assistance completing this application.